Building Energy
Key Points
- All combustion facilities at BBC
premises must be adequately maintained to prevent the release of
'dark smoke' or causing a nuisance.
- All combustion facilities at BBC
premises must have the relevant authorisations covering both the
design of the approval of the design and the height of the
chimney.
- All BBC premises must meet the
requirements of Part L of the Building Regulations.
- Any BBC premises where the
installed combustion capacity exceeds 20 MW [individually] or where
the installed combustion capacity exceeds 50MW [aggregated] must be
covered by a Pollution Prevention Control [PPC]
Permit.
- Any BBC premises where the
installed combustion capacity exceeds 20 MW is required to operate
within the requirements of the EU Emissions Trading
Scheme.